| It has been along time since i updated this thread.
I have made some progress since last time. The liner was installed in November and bottom drain cut and sealed. Water was fill have way and winter rain and snow add 15" plus to the water. The TPR and skimmer was not cut this is how i left the pond over winter. The pond was drained in March and liner fold were taped TPR cut and sealed.
Rocks was placed on the back side of the pond. Granit cobler on front edge. I used 4" block on the top course to create a step for the cobler. I didn't want any liner exposed.
The front wall has the first coat of stucco Done with wire lathe and mortar.
You can also see new concrete tied into the old and brick paver layed on top of the concete pad. I'm still working on the pavers. |